Get the latest load shedding updates, analysis and practical tips to deal with the continuous Eskom power cuts.
The 67.6% of respondents still on the national grid say dealing with blackouts has become second nature. The group also wants fair compensation for the damage caused by rolling blackouts and for the government to play open cards about South Africa’s energy crisis. There are, however, tight limits on what the President can really achieve, and anyone expecting a short-term solution to South Africa’s power crisis will be disappointed. [Choose the right-size gas geyser to save on electricity and money](https://www.dailymaverick.co.za/article/2022-11-06-choose-the-right-size-gas-geyser-to-save-on-electricity-and-money/) Several South African politicians and business people have instructed a legal team from seven law firms to demand that the government stops cutting the country’s power. [South Africans make a plan in the face of never-ending electricity blackouts](https://www.dailymaverick.co.za/article/2022-10-10-south-africans-make-a-plan-in-the-face-of-never-ending-electricity-blackouts/) [South Africans urged to use water sparingly as rolling blackouts hit precious resource](https://www.dailymaverick.co.za/article/2023-01-16-south-africans-urged-to-use-water-sparingly-amid-blackouts/) [Load shedding menu: Leftover pasta salad](https://www.dailymaverick.co.za/article/2023-01-16-south-africans-urged-to-use-water-sparingly-amid-blackouts/) [New law planned to accelerate power capacity in South Africa](https://www.dailymaverick.co.za/article/2023-01-17-new-law-planned-to-accelerate-power-capacity-in-south-africa/) [Government plans to focus on six ailing power stations to resolve the electricity crisis](https://www.dailymaverick.co.za/article/2023-01-16-government-plans-to-focus-on-six-ailing-power-stations-to-resolve-the-electricity-crisis/) [Gatvol citizens threaten Eskom and government with legal action, demand stop to rolling blackouts](https://www.dailymaverick.co.za/article/2023-01-16-blackouts-s-africans-threaten-eskom-government-with-legal-action/) [Out in the cold – power crisis forces enterprising ice-cream shops to brink of closure](https://www.dailymaverick.co.za/article/2023-01-17-out-in-the-cold-power-crisis-forces-enterprising-ice-cream-shops-to-brink-of-closure/)
Energy expert at Hohm Energy, Matthew Cruise, says that South Africa is likely to hit beyond stage 8 load shedding, warning that, contrary to promises from ...
“But I do see us going above stage 8 load shedding – because it’s just an arbitrary level,” he said. “A national blackout will have massive implications, and every effort is made to prevent this from occurring. “What would happen if that (stage 20) were to take place? ” If you add that to the current levels of load shedding, it’s clear we’re going to go to stage 8 and beyond – even so far as stage 10.” This is what municipalities have had a plan for since 2018 when the schedules were revised. Eskom’s official load shedding stages only go as high as stage 8.
A lot of things in this life are uncertain, but your load-shedding schedule does not have to be. With a week of stage 6 behind us, Eskom is bouncing between ...
[https://www.eskom.co.za/eas/energy-saving-tips-energy-advisory-service-eskom/](https://www.eskom.co.za/eas/energy-saving-tips-energy-advisory-service-eskom/) In a press release issued yesterday, January 16, Eskom stated that it expects 14 generators across the country to return to service in the following week. [First-of-its-kind concert to be hosted in Kruger National Park](https://lowvelder.co.za/810603/first-of-its-kind-concert-to-hosted-in-kruger-national-park/)
NUM said that load shedding could be avoided if the government had moved with greater speed to implement the commitments of the Eskom Social Compact.
How can such an old and retired engineer remember the plant components?” the union said. “Also, the issue of replacement, breakdown and maintenance spares has been a permanent problem. “The challenges to these power stations is known.
Load shedding has been slightly eased by Eskom to Stage 4 from 5am to 4pm daily with Stage 5 kicking in thereafter.
There are currently 12 generators out on planned maintenance," Eskom said. "Eskom cautions the public, however, that there is a high degree of uncertainty associated with this and that these changes will only be possible in their entirety if the units return to service as planned. "Eskom procured an additional 50 million litres of diesel on 06 January 2023.
Residents of Emalahleni and surrounding areas should take note of the load-shedding schedule issued by the Local Municipality.
[Clewer](https://witbanknews.co.za/204254/clewer-inwoners-bly-nou-in-stink-straat/), Ogies, Phola, Doornpoort, and Rietspruit Substations will be affected from 19:00 until 21:30. [GaNala](https://witbanknews.co.za/204082/kriel-was-in-high-spirits-for-sports-day/) and KwaGuqa Substations will be affected from 21:00 until 23:30. Various areas will be affected. Grobler Substation will be affected from 15:00 until 17:30. [KwaGuqa](https://witbanknews.co.za/203677/emalahleni-local-municipality-addresses-misinformation-regarding-kwaguqas-transformer/) Substations will be affected from 13:00 until 15:30. Grobler Substation will be affected from 07:00 until 09:30.
The ailing parastatal said stage 4 load-shedding will be implemented at 05:00 to 16:00 daily, from Tuesday morning, with stage 5 load-shedding daily from ...
“A generating unit each at Kendal, Majuba and Tutuka power stations have returned to service today. A further update will be published as soon as any significant changes occur,” Mantshantsha added. Together, these emergency generators contribute 5 700MW of capacity.”